Spain is experiencing a decisive moment in its energy policy. While the Government defends an orderly closure of nuclear power plants and relies on an experimental digital system to stabilize the grid, large electricity companies warn that the transition It is being faster than safe. At the epicenter of this tension is Almaraz, the Extremaduran power plant that refuses to turn off its reactors and that has once again divided technicians, politicians and neighbors.
The nuclear dilemma. The closure of the Almaraz nuclear power plant in Cáceres is officially set for 2027 and 2028, but the debate over its future has returned with force. Iberdrola, Endesa and Naturgy agreed to present to the Ministry for the Ecological Transition a formal request to extend their activity until 2030. They will do so, they say, out of “responsibility with the supply” after the voltage failures recorded in recent weeks that “they reactivated the risk of blackout”.
Companies have, for the moment, given up asking for tax reductions. Their message is different: Spain, they argue, is not prepared to disconnect from the atom. “Nuclear is the system’s anti-blackout shield,” says the CEO of Iberdrola Spain. However, the Government does not move. The Minister for the Ecological Transition, Sara Aagesen, has reiterated the commitment to the closure calendar agreed in 2019, which foresees the nuclear blackout between 2027 and 2035. Only if three conditions are not met: security, guarantee of supply and zero cost for the taxpayer, will the Executive would reconsider his position.
A model in testing. The core of the controversy is not only political, but technical. The Executive’s plan involves replacing the stability offered by nuclear and thermal plants with a digital voltage and frequency control system based on renewables. In theory, wind and solar farms will be able to simulate electrical inertia —the ability to resist sudden changes in frequency— through advanced electronics. In practice, the model is still in the testing phase.
According to Energy NewsRed Eléctrica (REE) is developing new control tools to integrate non-synchronous generation, but still without complete validation. Additionally, new digital control algorithms have not been tested on a national scaleand its reliability at high power has not yet been demonstrated. Sources from the Ministry of Ecological Transition cited by El Periódico They admit that full stability of the system “will only be possible when all renewable plants are digitally synchronized with the operator”, a process that – they acknowledge – “will still take time.”
The network under surveillance. Aware of these risks, the CNMC approved an emergency modification of the operating procedures (OP 3.1, 3.2, 7.2 and 7.4) to reinforce the stability of the system. In practice, they are standards that determine how Red Eléctrica must react to variations in voltage and frequency, and allow it to act with more flexibility in times of risk.
However, not everything went as planned. As energy expert Joaquín Coronado explains on his networksthe CNMC stopped the complete approval of OP 7.4 when it detected that the new model required responses that were impossible for many conventional plants to comply with. Several generators alleged that too rapid a reaction could damage the machines or generate additional oscillations, something the CNMC acknowledged in its resolution. The regulator asked Red Eléctrica to “intensify coordination and temporarily make the requirements more flexible”, making it clear that the problem was not one of inertia, but rather speed of response.
A pulse of time. The electricity companies’ proposal to extend the first Almaraz reactor until 2030 and the second until 2029, would give three additional years to the current calendar. However, the Nuclear Safety Council requires that documentation be submitted before November 1 to begin the decommissioning process.
In parallel, the Government of Extremadura has announced that it will reduce the regional “ecotax” by half if the plant remains operational, a gesture that the central Executive views with suspicion. “Taxpayers cannot pay more to maintain a plant that had to close,” recalled the Government delegate in Extremadura, José Luis Quintana, in statements to Canal Extremadura.
Mobilization in the streets. While the technical and political debate becomes entangled, the residents of Almaraz took to the streets. Last Marchhundreds of people marched under the slogan “Yes to Almaraz, yes to the future,” in a protest supported by mayors of nearby municipalities and nuclear sector associations. In their arguments they defend their position in favor of nuclear power for fear of job loss, a population exodus and the fall of the local economy.
But not everyone shares that enthusiasm. Ecologists in Action criticized the presence of local authorities at the protest and asked to accelerate a “just transition” that generates employment alternatives. “You cannot continue tying the future of a region to an industry that promotes environmental and health risks,” the organization said in a statement.
Europe looks at Spain. While France and Belgium extend the life of their reactors until 2060, Spain remains firm in its nuclear closure. The Enresa fund to dismantle the plants drags a deficit of 11.6 billion euros. The electricity companies cite this as proof that closing early makes the system more expensive; The Government replies that extending it would jeopardize the ecological transition.
The peninsula remains an “energy island” with only 3% interconnection with France, which amplifies any failure. And more and more experts repeat the same thing: the problem is not the speed of the transition, but that the network and the rules They are not getting stronger at the same rate..
A still uncertain future. Almaraz has become much more than a power plant: it is a symbol of the tension between climate urgency and energy security. The Executive insists that Spain will be able to sustain its network with renewable technology and digital control; Technicians and electrical companies ask for caution.
Meanwhile, Red Eléctrica engineers fine-tune algorithms, the CNMC approves regulatory patches and the residents of Almaraz prepare for a future that, for now, continues to depend on its two reactors. Spain wants to turn on the light of tomorrow, but the switch, for now, remains in the hands of a power plant that refuses to die.