The AVE to Extremadura has taken a key step in its connection with Madrid. It’s a small step that takes us back a decade.

They say that things in the palace go slowly. We could say the same about high speed. Not only because “high-speed” trains are taking longer than ever, but also because the construction of each new line resembles a birth that lasts decades.

For example, the AVE to Extremadura. A quarter of a century has now passed since the project was approved. 25 years. And what we continue to have are connections typical of the 70s until we enter Extremadura where, coincidentally, the pace is already accelerating past Cáceres.

We don’t lie. In 1970whoever took a train to Extremadura would arrive at the current Monfragüe station in 181 minutes. Today if everything goes well it will only take 20 minutes less. More than half a century after passing times collected in this guideit still takes more than three hours to get from Madrid to Plasencia. And right now it is necessary to stop at the aforementioned station and take a bus because the train no longer goes there.

At least, in Extremadura they can boast since last December of having Cáceres and Badajoz connected, now, by high speed. Since the last days of the year, it is possible to cover the journey in 50 minutes. It is the result of works that, although they have taken time, have ended up being completed.

A milestone that they cannot boast of in Castilla-La Mancha. And, 25 years after beginning to study where the AVE will pass on its way to Lisbon, a new step forward has been taken. One that also takes us almost ten years back.

One step forward, Toledo. One step back

When it was planned that an AVE would connect Madrid with Extremadura, it was decided that the work would have two large, clearly differentiated sections. One of them would be Madrid-Oropesa, the second Talayuela-Cáceres.

With its obvious delaysthat second section is close to completion and its completion past Cáceres is what has allowed the arrival of high speed in that interprovincial Extremaduran section. And, as they point out in this great review of the diary Today Despite all the dates that have occurred in this quarter of a century, the end of the project could have been very advanced if the La Mancha section had been built at the same speed.

However, since 2008 the various parties involved have been discussing what to do with the passage through Toledo. Or, rather, whether or not the train should pass through Toledo. That year, with the environmental impact report of the Madrid-Oropesa section already approved, the final approval was given to the informative study that contemplated a connection with the Andalusian corridor next to the Toledo town of Pantoja. The idea was to take a branch of this line towards Extremadura and thus save costs.

The works, however, were not carried out. The 2008 crisis wiped out the project and it was never launched. Without machines working, the environmental report expired and that was when the Ministry of Public Works indicated that the AVE would pass through Toledo. We are already in 2017.

The Government’s proposal was that, by passing through Toledo, the line would attract a greater number of travelers since the line would connect with a city that is a World Heritage Site. Of course, this meant traveling more kilometers and increasing travel time because Toledo is located further south than the first proposal.

The idea was rejected by local authorities from the first moment. And the passage through Toledo It’s delicate. The Executive’s proposal has always been to take the AVE to the current station, which is just two kilometers in a straight line from the city center. But that means building a viaduct to overcome the passage of the Tagus, which has received continued rejection from local governments and the neighborhood platforms that consider that the image of the city would be damaged. Their proposal was to build a new station in a nearby industrial estate.

This is how the year 2020 was reached, with an informative study in which it was proposed to subdivide the section into four parts: Toledo, Torrijos, Talavera de la Reina and Oropesa. They also showed their rejection of this project in Torrijos, which led to more bureaucracy and carrying out a complementary study in 2022. This document was presented in 2024 and had the approval of this town the following year… but in Toledo, as we have said, they still do not view the project favorably.

In order to streamline the project, finally The Ministry of Transport has finally approved a new informative study that would contemplate building two branches from the Andalusian corridor. They explain in Today that if the branch goes ahead it would have its origin in Pantoja (as planned from 2008 to 2017) and that it would allow passage in both directions with trains of Iberian width and international width. However, it would be necessary to use trains capable of making this jumpsince the rest of the route to Extremadura is built on Iberian gauge.

That is, right now what is being studied is the same to the conclusion that It was arrived in 2008 and that remained on the agenda until 2017. At least, as an alternative until it is decided whether or not the AVE to Extremadura passes through Toledo. And, if it happens, where is it going to do it.

Photo | Gunnar Ridderström, Jaime Lillo and Falk2

In Xataka | The theory said that the entry of the AVE into Galicia would plummet aircraft prices. Practice is something else

Leave your vote

Leave a Comment

GIPHY App Key not set. Please check settings

Log In

Forgot password?

Forgot password?

Enter your account data and we will send you a link to reset your password.

Your password reset link appears to be invalid or expired.

Log in

Privacy Policy

Add to Collection

No Collections

Here you'll find all collections you've created before.